The Research on Delay Propagation of Urban Rail Transit Operation under Sudden Failure

Table 1

Operation delay of urban rail transit.

Main categorySubcategoryFrequency (times/year)Average processing time (min)Proportion (%)

Train factorsTrain failure, door, auxiliary control circuit, control circuit, brake, main circuit12717.630.75
Communication signal factorATS, vehicle ATC, trackside equipment, communication, signal, etc.18418.244.55
Power supply factorsSubstation, touch network, power supply, etc.823.41.94
Public works factorsTurnouts, lines227.65.33
Passenger transportation factorsScreen door/safety door, driver delay, passenger transportation, and others1414.33.39
Objective factorsPassengers, people and objects, intrusion limits, large passenger flow, personnel invasion, human-train conflict, objectives, and others583.314.04