Research Article

Magnitude of Construction Cost and Schedule Overruns in Public Work Projects

Table 4

Mean and median values of construction cost overrun by project factors.

Project factorsCategoriesNo. of projectsConstruction cost overrun (%)
Mean MedianStandard deviation

Project typesFlood control833.040.008.87
Transportation2363.230.175.99
Utilities441.270.004.33

Project sizeLess than $1 million1351.670.005.83
$1 million to $5 million1283.550.765.59
Greater than $5 million 1003.921.758.38

Project construction durationLess than 1 year2792.460.005.85
Greater than 1 year844.592.128.54

Project completion yearFrom 1991 to 20001852.660.006.69
From 2001 to 20081783.250.006.54

Total projectsā€‰3632.950.006.62