Magnitude of Construction Cost and Schedule Overruns in Public Work Projects
Table 4
Mean and median values of construction cost overrun by project factors.
| Project factors | Categories | No. of projects | Construction cost overrun (%) | Mean | Median | Standard deviation |
| Project types | Flood control | 83 | 3.04 | 0.00 | 8.87 | Transportation | 236 | 3.23 | 0.17 | 5.99 | Utilities | 44 | 1.27 | 0.00 | 4.33 |
| Project size | Less than $1 million | 135 | 1.67 | 0.00 | 5.83 | $1 million to $5 million | 128 | 3.55 | 0.76 | 5.59 | Greater than $5 million | 100 | 3.92 | 1.75 | 8.38 |
| Project construction duration | Less than 1 year | 279 | 2.46 | 0.00 | 5.85 | Greater than 1 year | 84 | 4.59 | 2.12 | 8.54 |
| Project completion year | From 1991 to 2000 | 185 | 2.66 | 0.00 | 6.69 | From 2001 to 2008 | 178 | 3.25 | 0.00 | 6.54 |
| Total projects | ā | 363 | 2.95 | 0.00 | 6.62 |
|
|