The Use of Project Time Management Processes and the Schedule Performance of Construction Projects in Mexico

Table 3

Information of contractors and projects observed in this study.

Information of contractorsProject
IDBusiness size Portion of annual production dedicated to school construction projectsTotal budget (US dollars)Scheduled duration (days)

1Small41–60%$219,67391
2Micro81–95%$228,56984
3Medium21–40%$192,00991
4Micro81–95%$140,00477
5Medium61–80%$455,57298
6Medium61–80%$242,209112
7Small81–95%$177,01998
8Small21–40%$182,31997