An Integrated Expert System for Linear Scheduling Heavy Earthmoving Operations

Table 2

Comparison of total project duration (days) for diverse soil material and volume.

⁢Soil type⁢Volume (LCY)⁢Actual⁢ProposedPercentage difference ⁢ (%)
Total duration (days)Amount of equipmentTotal duration (days)Amount of equipment

Moraine41,975674631
Granular16,250383216
Rock274,45218813727