An Integrated Expert System for Linear Scheduling Heavy Earthmoving Operations
Table 2
Comparison of total project duration (days) for diverse soil material and volume.
| Soil type | Volume (LCY) | Actual | Proposed | Percentage difference (%) | Total duration (days) | Amount of equipment | Total duration (days) | Amount of equipment |
| Moraine | 41,975 | 67 | | 46 | | 31 | Granular | 16,250 | 38 | | 32 | | 16 | Rock | 274,452 | 188 | | 137 | | 27 |
|
|