Deviations between Contract Sums and Final Accounts: The Case of Capital Projects in Ghana

1Building and Road Research Institute, CSIR, Kumasi, Ghana
2Attachy Construction Limited, Kumasi, Ghana

Received 8 February 2016; Revised 22 April 2016; Accepted 12 May 2016

Academic Editor: Eul-Bum Lee

Copyright © 2016 Kofi Offei-Nyako et al. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

Linked References

  1. G. E. Oseghale and A. B. Wahab, “Analysis of relationship between preliminary estimate, tender sum and final accounts (a case study of selected building projects in Edo State, Nigeria),” Journal of Civil and Environmental Research, vol. 6, no. 6, p. 76, 2014. View at Google Scholar
  2. L. S. Pheng and K. H. Ming, “Formulating a strategic marketing mix for quantity surveyors,” Marketing Intelligence & Planning, vol. 15, no. 6, pp. 273–280, 1997. View at Publisher · View at Google Scholar
  3. D. Cartlidge, Bills of Quantities, 2009, http://www.isurv.com/site/scripts/documents.aspx?categoryID=303.
  4. P. R. Davis, P. E. D. Love, and D. Baccarini, “Bills of quantities: nemesis or nirvana?” Structural Survey, vol. 27, no. 2, pp. 99–108, 2009. View at Publisher · View at Google Scholar · View at Scopus
  5. A. Razali, A. Tajudin, A. Fadzli, and A. Tajuddin, “Applicability of bill of quantities in construction procurement,” International Journal of Engineering Science Invention, vol. 3, no. 7, pp. 31–34, 2014. View at Google Scholar
  6. F. Vivien and P. Nataliya, “Ghana's infrastructure; A continental perspective,” in Policy Research Working Paper 5600, World Bank, 2011. View at Google Scholar
  7. L. Ashworth, Cost Studies of Building, Harlow Longman, London, UK, 2nd edition, 1994.
  8. M. O. Oboirien, Tendering and Estimating for Building Students, Best Way Printers, Auchi, Nigeria, 1st edition, 2006.
  9. M. Arafa and M. Alqedra, “Early stage cost estimation of buildings construction projects using artificial neural networks,” Journal of Artificial Intelligence, vol. 4, no. 1, pp. 63–75, 2011. View at Publisher · View at Google Scholar
  10. Y. Frimpong, J. Oluwoye, and L. Crawford, “Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study,” International Journal of Project Management, vol. 21, no. 5, pp. 321–326, 2003. View at Publisher · View at Google Scholar · View at Scopus
  11. C. Kaliba, M. Muya, and K. Mumba, “Cost escalation and schedule delays in road construction projects in Zambia,” International Journal of Project Management, vol. 27, no. 5, pp. 522–531, 2009. View at Publisher · View at Google Scholar · View at Scopus
  12. H. A. Odeyinka, S. Kelly, and S. Perera, “An evaluation of the budgetary reliability of bills of quantities in building procurement,” in Proceedings of the Construction and Building Research Conference of the Royal Institution of Chartered Surveyors, pp. 435–446, University of Cape Town, Cape Town, South Africa, September 2009.
  13. N. Azhar, R. U. Farooqui, and S. M. Ahmed, “Cost overrun factors in construction industry of Pakistan,” in Proceedings of the 1st International Conference on Construction in Developing Countries (ICCIDC–I) “Advancing and Integrating Construction Education, Research & Practice”, 2008.
  14. A. Enshassi, J. Al-Najjar, and M. Kumaraswamy, “Delays and cost overruns in the construction projects in the Gaza Strip,” Journal of Financial Management of Property and Construction, vol. 14, no. 2, pp. 126–151, 2009. View at Publisher · View at Google Scholar
  15. O. J. Ameh, A. A. Soyingbe, and K. T. Odusami, “Significant factors causing cost overruns in telecommunication projects in Nigeria,” Journal of Construction in Developing Countries, vol. 15, no. 2, pp. 49–67, 2010. View at Google Scholar
  16. K. Larkin, H. Odeyinka, and R. Eadie, “An exploration of theoretical concepts and methods for assessing risk impacts on the variability between contract sum and final account in design and build projects,” in Proceedings of the 28th Annual ARCOM Conference, S. D. Smith, Ed., pp. 337–346, Association of Researchers in Construction Management, Edinburgh, UK, September 2012. View at Scopus
  17. T. Cunningham, Factors Affecting the Cost of Building Work—An Overview, Dublin Institute of Technology, 2013.
  18. G. D. Israel, Statistical Formula for Sample Size Determination, 2007.
  19. E. Lim and J. Alum, “Construction productivity: issues encountered by contractors in Singapore,” International Journal of Project Management, vol. 13, no. 1, pp. 51–58, 1995. View at Publisher · View at Google Scholar · View at Scopus
  20. P. Legendre, “Coefficient of concordance,” in Encyclopedia of Research Design, N. J. Salkind, Ed., vol. 1, pp. 164–169, SAGE Publications, Los Angeles, Calif, USA, 2010. View at Google Scholar