Risk Level Assessment in Construction Projects Using the Schedule Performance Index

Table 2

Durations and delays.

IDPlanned durationFinal durationDelaySPI3SPI6SPI9SPI12

Project 012543180.79380.41020.34920.3539
Project 021836181.05160.84110.56850.5578
Project 032543180.00000.23660.19350.1927
Project 042757301.30980.72790.53380.4197
Project 052255331.02730.75990.60910.4803
Project 062434100.66281.35951.20690.9597
Project 072846180.65280.74440.52350.4082
Project 082135140.90390.76930.67990.7227
Project 092639130.00000.16030.35290.3229
Project 10253270.51310.69800.74020.6722
Project 11253270.71290.63900.64140.5929
Project 12192560.95040.89430.87290.7664
Project 13242510.86440.88110.98980.9366
Project 14232630.89500.83390.87710.8453
Project 15303000.99661.00020.98930.9899
Project 16282801.00000.59190.87220.8210
Project 17323201.00001.51981.18201.1319
Project 18323640.97641.00101.00650.9767
Project 19212101.10341.10341.14601.2981