Research Article

Diagnosing the Causes of Failure in the Construction Sector Using Root Cause Analysis Technique

Table 3

Main causes weight, relative importance, and rank.

NoCodeWeights of Main CausesAverage Weights of Main CausesRelative Importance RIRank
Project Management Process GroupsMain Causes

1S1S1162.796816
2S1266.51
3S1374.41

1S2S2174.7673.2817.4
2S2268.13
3S2371.86
4S2478.37

1S3S3176.0469.1816.4
2S3269.30
3S3368.60
4S3462.79

1S4S4179.3074.0317.6
2S4275.93
3S4382.90
4S4473.72
5S4562.20
6S4667.20
7S4776.97

1S5S5170.4671.0816.8
2S5272.79
3S5379.30
4S5474.41
5S5565.46
6S5666.27
7S5782.09
8S5871.97
9S5966.74
10S51067.67
11S51163.02
12S51272.55
13S51371.39

1S6S6162.9067.0615.8
2S6264.76
3S6372.55
4S6468.02

āˆ‘422.63 100%