Cost-Benefit Analysis for the Concentrated Solar Power in China
Table 2
Parameters values and data related to the CSP systems of China.
| Basic parameter | Values |
| Benchmark FIT (P) [2] | RMB1.15/kWh | Initial investment (II) | See Table 1 | O&M costs ratio (OM) [29] | 2% | Operation period () [29] | 25 years | Repayment period [31] | 15 years | Long-term loan rate (r) | 4.9% | VAT rate () [22] | 17% | Additional taxes ratio () [22] | 8% | Proportion of self-consumption electricity () [31] | 10% | Annual generation electricity () | See Table 1 | Construction costs ratio (C) [26] | 96% | Insurance expenses ratio (I) [14, 30] | 0.5% | Construction period () [28] | 2 years | Depreciation period [22] | 15 years | Discount rate () [31] | 10% | Income tax rate () [22] | 15% | Loan ratio [28] | 80% |
|
|