Research Article
Improvement of the Voltage Profile and Loss Reduction in Distribution Network Using Moth Flame Algorithm: Wolaita Sodo, Ethiopia
Table 1
Distribution line voltage (kV) variation for peak time 8:00–21:00.
| Time (s) | Gesuba line 1 (kV) | Sodo line 2 (kV) | Bodit line 4 (kV) | Bilate line 5 (kV) | 33 kV Abala line 2 (kV) | 33 kV Bedesa line 3 (kV) |
| 8:00 | 14.8 | 14.6 | 14.8 | 14.8 | 32.7 | 32.8 | 9:00 | 14.7 | 14.5 | 14.8 | 14.8 | 32.8 | 32.7 | 10:00 | 15 | 14.7 | 14.7 | 14.7 | 32.8 | 32.7 | 11:00 | 14.7 | 14.2 | 15 | 15 | 33 | 33 | 12:00 | 15 | 14.68 | 15 | 15 | 33.1 | 33 | 13:00 | 15 | 14.2 | 15 | 15 | 33 | 33 | 14:00 | 15 | 14.65 | 15 | 15.1 | 32.8 | 32.7 | 15:00 | 14.8 | 14.6 | 14.8 | 15 | 32.7 | 32.7 | 16:00 | 15.1 | 14.7 | 15.1 | 14.8 | 32.8 | 32.8 | 17:00 | 15 | 14.67 | 15 | 15.1 | 33 | 33.1 | 18:00 | 15 | 14.76 | 15 | 15 | 33 | 33 | 19:00 | 14.8 | 14.7 | 15 | 15 | 33 | 33 | 20:00 | 15 | 14.5 | 14.9 | 14.9 | 32.9 | 33 |
|
|