400 kV double circuit HVAC investment cost

ItemTotal cost (USD)

Transmission line cost from Tana Beles to Sululta255,065,116.51
Tana Beles switchyard upgrading6,238,633.51
Sululta substation upgrading13,439,557.28
Total cost274,743,307.30
Engineering and administration (5% of the total cost)13,737,165.37
Total project cost288,480,472.67
Physical contingency (5% of the total cost)14,424,023.63
Price contingency (10% of the total project cost)28,848,047.27
Grand total331,752,543.56