Research Article
Development of a Cost-Effective Solar/Diesel Independent Power Plant for a Remote Station
Table 1
Remote station daily load demand.
| S/N | Power consumption | Power (W) | Quantity | Load (W) | Load (kW) | Hour/day | On-time (time in use) |
| 1 | Air condition | 2000 | 18 | 36000 | 36 | 8 | 08:00–16:00 | 2 | Fans | 56 | 78 | 4368 | 4.368 | 8 | 08:00–16:00 | 3 | Lighting | 40 | 152 | 6080 | 6.08 | 8 | 08:00–16:00 | 4 | Printers | 800 | 11 | 8800 | 8.8 | 8 | 08:00–16:00 | 5 | Desktop computer | 264 | 14 | 3696 | 3.696 | 8 | 08:00–16:00 | 6 | Security light | 60 | 9 | 540 | 0.54 | 8 | 08:00–16:00 | 7 | Refrigerator | 100 | 12 | 1200 | 1.2 | 8 | 08:00–16:00 | 8 | Pumping machine | 1119 | 1 | 1119 | 1.119 | 2 | 10:00–12:00 | 9 | Television | 60 | 12 | 720 | 0.72 | 4 | 12:00–16:00 | 10 | Tachometer | 16.1 | 1 | 16.1 | 0.016 | 3 | 13:00–16:00 | 11 | Transformer trainer | 600 | 1 | 600 | 0.6 | 3 | 13:00–16:00 | 12 | Feedback power tester | 675 | 1 | 675 | 0.675 | 3 | 13:00–16:00 | 13 | Battery charger | 4400 | 1 | 4400 | 4.4 | 6 | 10:00–16:00 | 14 | System trainer | 4.56 | 1 | 4.56 | 0.00456 | 3 | 13:00–16:00 | 15 | Projector | 210 | 2 | 420 | 0.42 | 6 | 10:00–16:00 | 16 | Thurlby PL(320) | 480 | 1 | 480 | 0.48 | 3 | 13:00–16:00 | 17 | Function generator | 500 | 1 | 500 | 0.5 | 3 | 13:00–16:00 | 18 | Photocopy machine | 1100 | 12 | 13200 | 13.2 | 6 | 10:00–16:00 | 19 | Soldering iron | 480 | 8 | 3840 | 3.84 | 7 | 09:00–16:00 | 20 | DC power supply | 375 | 1 | 375 | 0.375 | 3 | 13:00–16:00 | 21 | Electric water heater | 2990 | 12 | 35880 | 35.88 | 2 | 08:00–10:00 | 22 | Oscilloscope | 255 | 3 | 765 | 0.765 | 3 | 13:00–16:00 | 23 | Signal generator | 1000 | 2 | 2000 | 2 | 3 | 13:00–16:00 | 24 | Feedback amplifier | 155.9 | 1 | 155.9 | 0.1559 | 3 | 13:00–16:00 |
|
|