Research Article

BIM Application to Select Appropriate Design Alternative with Consideration of LCA and LCCA

Table 3

LCA and LCCA results for each alternative.

Building skin systemOriginal skinAlt. 1Alt. 2

LCA results
(kg)
CO2 emission in
construction phase
ManufacturingAluminum frame839,987750,011839,987
Glass100,43239,121104,346
Cement brick21,391
Mortar16,873
Polystyrene826
Concrete13,231
Argon453
Construction940,419841,453944,786
CO2 emission in
operation phase
Energy consumptionOne year (kg/yr)668,310675,572659,745
40 years (kg)26,732,40027,022,88026,389,800
CO2 emission in
disposal phase
Disposal (kg)21104 22
Total amount of CO2 emission27,672,400 (kg)27,864,438 (kg)26,389,800 (kg)

LCCA results
(US $)
Construction phaseInitial investment costs 191,220 196,924 223,988
Operation phaseReplacement and maintenance costs136,765 132,938 160,201
Energy costs8,204,352 8,359,094 7,935,464
Disposal phaseDisposal costs9,565 14,507 10,154
Total amount costs $8,541,902 $8,703,462 $8,329,808