Research Article
Efficient Heuristic Algorithm for Scheduling Two-Stage Hybrid Flowshop with Sequence-Dependent Setup Times
Table 1
Comparison between 3D-AOI-PPP and 2S-HFS-SDST-SP.
| ā | 3D-AOI-PPP | 2S-HFS-SDST-SP |
| Problem configurations | FOVs to be inspected | Jobs to be done | One camera | Single machine at Stage 1 | Multiple CPU cores | Identical parallel machines at Stage 2 | Shooting time | Processing time at Stage 1 | Image processing time | Processing time at Stage 2 | Move time between two FOVs | Sequence-dependent setup time between two jobs |
| Decision variable | Visit sequence of all FOVs | Operation sequence of all jobs |
| Objective functions | Minimize total working time | Minimize makespan |
|
|