Research Article

An Adapted Firefly Algorithm for Product Development Project Scheduling with Fuzzy Activity Duration

Table 3

Activities’ start times and finish times.

Activity numberFuzzy start timeFuzzy finish time

1(0, 0, 0, 0)(0, 0, 0, 0)
2(0, 0, 0, 0)(4, 6, 9, 12)
3(4, 6, 9, 12)(11, 15, 20, 26)
4(11, 15, 20, 26)(17, 23, 30, 38)
5(4, 6, 9, 12)(11, 14, 19, 23)
6(11, 15, 20, 26)(13, 18, 25, 32)
7(17, 23, 30, 38)(22, 30, 38, 48)
8(22, 30, 38, 48)(31, 42, 52, 64)
9(31, 42, 52, 64)(31, 42, 52, 64)