An Improved Performance Measurement Approach for Knowledge-Based Companies Using Kalman Filter Forecasting Method

Table 3

The information of the project.

CodeActivityPredecessorsDuration (days)EVPV% complete

1Application design project58218,200.0110,166.776%
2Technical52212,333.360,000.086%
3Server delivery123,333.33,333.3100%
4Technical activities based panel maker android apps32402,700.012,000.0100%
5Bug Fixes instrument panel Android app4600.02,000.010%
6Technical activities building up the base panel32402,700.012,000.090%
7Fix-up panel construction6600.02,000.050%
8Technical activities based panel maker IOS app32003,600.013,333.395%
9Bug Fixes instrument panel IOS app8600.02,666.750%
10Connect to payment (panel and apps)4, 6, 82400.0666.7100%
11Technical support during operation10300.010,000.00%
12Launch site for introducing and selling account6, 15600.02,000.0100%
13Connect to the SMS system6300.00.0100%
14Design and graphics303,066.73,333.393%
15Panel UI design and graphics19302,400.02,666.790%
16Logo design1915666.7666.7100%
17Branding and marketing5522,800.038,333.345%
18Determine the target market area and channels to market19602,000.04,000.050%
19Evaluation and selection of brand (scope)30800.01,000.080%
20Advertising and marketing18, 11300.033,333.30%
21Content3300.08,500.09%
22Education portal launched6150.0500.050%
23Finalizing the app version12140.01,000.00%
24Drafting contractual documents with users to investigate and solve the problem of legal and contractual issues23320.01,000.00%
25Film production and educational content app maker18, 11300.05,000.010%
26The closing activities25, 20300.01,000.00%