| Code | Activity | Predecessors | Duration (days) | EV | PV | % complete |
| 1 | Application design project | — | 582 | 18,200.0 | 110,166.7 | 76% | 2 | Technical | — | 522 | 12,333.3 | 60,000.0 | 86% | 3 | Server delivery | — | 12 | 3,333.3 | 3,333.3 | 100% | 4 | Technical activities based panel maker android apps | 3 | 240 | 2,700.0 | 12,000.0 | 100% | 5 | Bug Fixes instrument panel Android app | 4 | 60 | 0.0 | 2,000.0 | 10% | 6 | Technical activities building up the base panel | 3 | 240 | 2,700.0 | 12,000.0 | 90% | 7 | Fix-up panel construction | 6 | 60 | 0.0 | 2,000.0 | 50% | 8 | Technical activities based panel maker IOS app | 3 | 200 | 3,600.0 | 13,333.3 | 95% | 9 | Bug Fixes instrument panel IOS app | 8 | 60 | 0.0 | 2,666.7 | 50% | 10 | Connect to payment (panel and apps) | 4, 6, 8 | 240 | 0.0 | 666.7 | 100% | 11 | Technical support during operation | 10 | 30 | 0.0 | 10,000.0 | 0% | 12 | Launch site for introducing and selling account | 6, 15 | 60 | 0.0 | 2,000.0 | 100% | 13 | Connect to the SMS system | 6 | 30 | 0.0 | 0.0 | 100% | 14 | Design and graphics | — | 30 | 3,066.7 | 3,333.3 | 93% | 15 | Panel UI design and graphics | 19 | 30 | 2,400.0 | 2,666.7 | 90% | 16 | Logo design | 19 | 15 | 666.7 | 666.7 | 100% | 17 | Branding and marketing | — | 552 | 2,800.0 | 38,333.3 | 45% | 18 | Determine the target market area and channels to market | 19 | 60 | 2,000.0 | 4,000.0 | 50% | 19 | Evaluation and selection of brand (scope) | — | 30 | 800.0 | 1,000.0 | 80% | 20 | Advertising and marketing | 18, 11 | 30 | 0.0 | 33,333.3 | 0% | 21 | Content | — | 330 | 0.0 | 8,500.0 | 9% | 22 | Education portal launched | 6 | 15 | 0.0 | 500.0 | 50% | 23 | Finalizing the app version | 12 | 14 | 0.0 | 1,000.0 | 0% | 24 | Drafting contractual documents with users to investigate and solve the problem of legal and contractual issues | 23 | 32 | 0.0 | 1,000.0 | 0% | 25 | Film production and educational content app maker | 18, 11 | 30 | 0.0 | 5,000.0 | 10% | 26 | The closing activities | 25, 20 | 30 | 0.0 | 1,000.0 | 0% |
|
|