A Novel Hybrid MCDM Procedure for Achieving Aspired Earned Value Project Performance

Table 8

Gaps indices obtained through the modified VIKOR method.

Dimension/factorInfluential weights (IWs)Performance valuesThe size of gap to aspiration level
LocalGlobal

EVM users ()0.2500.4080.653
 Experience () 0.2010.0503.3501.9440.4130.764
 Training ()0.1960.0493.7502.6670.3130.583
 Administrative capabilities ()0.1980.0503.5502.7220.3630.569
 Technical capabilities ()0.2100.0533.2002.7780.4500.556
 Changes in work contents ()0.1950.0493.0001.8330.5000.792
EVM methodology ()0.2510.3950.600
 WBS ()0.2060.0524.0002.8330.2500.542
 CPM ()0.1960.0493.5001.7220.3750.819
 IPT ()0.2180.0553.3002.8890.4250.528
 Computer system ()0.1730.0433.1003.0560.4750.486
 Integrated project management () 0.2070.0523.2002.5000.4500.625
Implementation process ()0.2560.4880.633
 Open communication ()0.2050.0533.0003.0560.5000.486
 Sufficient resources ()0.1780.0452.9502.0560.5130.736
 Top-down approach ()0.1840.0473.3002.4440.4250.639
 Integrated change control system ()0.2150.0553.3502.5000.4130.625
 Continuous improvement () 0.2180.0562.6502.2780.5880.681
Project management environment ()0.2430.5180.753
 Colleague-based work environment ()0.2060.0503.0001.7220.5000.819
 Ownership of EVM to lower level project managers ()0.2010.0492.9002.2780.5250.681
 Risk free ()0.2080.0512.8001.8330.5500.792
 Culture () 0.2060.0502.7502.3890.5630.653
 Regulations ()0.1780.0433.2001.7220.4500.819

Gap indices0.5200.739