Research Article
Optimization of Gantry Crane Scheduling in Container Sea-Rail Intermodal Transport Yard
Table 5
Moving times of gantry crane between each pair of blocks.
| Move time | Block | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
| Block | 1 | 0 | 1 | 2 | 3 | 8 | 9 | 10 | 11 | 11 | 12 | 13 | 14 | 14 | 15 | 16 | 17 | 2 | 1 | 0 | 1 | 2 | 9 | 8 | 9 | 10 | 12 | 11 | 12 | 13 | 15 | 14 | 15 | 16 | 3 | 2 | 1 | 0 | 1 | 10 | 9 | 8 | 9 | 13 | 12 | 11 | 12 | 16 | 15 | 14 | 15 | 4 | 3 | 2 | 1 | 0 | 11 | 10 | 9 | 8 | 14 | 13 | 12 | 11 | 17 | 16 | 15 | 14 | 5 | 8 | 9 | 10 | 11 | 0 | 1 | 2 | 3 | 8 | 9 | 10 | 11 | 11 | 12 | 13 | 14 | 6 | 9 | 8 | 9 | 10 | 1 | 0 | 1 | 2 | 9 | 8 | 9 | 10 | 12 | 11 | 12 | 13 | 7 | 10 | 9 | 8 | 9 | 2 | 1 | 0 | 1 | 10 | 9 | 8 | 9 | 13 | 12 | 11 | 12 | 8 | 11 | 10 | 9 | 8 | 3 | 2 | 1 | 0 | 11 | 10 | 9 | 8 | 14 | 13 | 12 | 11 | 9 | 11 | 12 | 13 | 14 | 8 | 9 | 10 | 11 | 0 | 1 | 2 | 3 | 8 | 9 | 10 | 11 | 10 | 12 | 11 | 12 | 13 | 9 | 8 | 9 | 10 | 1 | 0 | 1 | 2 | 9 | 8 | 9 | 10 | 11 | 13 | 12 | 11 | 12 | 10 | 9 | 8 | 9 | 2 | 1 | 0 | 1 | 10 | 9 | 8 | 9 | 12 | 14 | 13 | 12 | 11 | 11 | 10 | 9 | 8 | 3 | 2 | 1 | 0 | 11 | 10 | 9 | 8 | 13 | 14 | 15 | 16 | 17 | 11 | 12 | 13 | 14 | 8 | 9 | 10 | 11 | 0 | 1 | 2 | 3 | 14 | 15 | 14 | 15 | 16 | 12 | 11 | 12 | 13 | 9 | 8 | 9 | 10 | 1 | 0 | 1 | 2 | 15 | 16 | 15 | 14 | 15 | 13 | 12 | 11 | 12 | 10 | 9 | 8 | 9 | 2 | 1 | 0 | 1 | 16 | 17 | 16 | 15 | 14 | 14 | 13 | 12 | 11 | 11 | 10 | 9 | 8 | 3 | 2 | 1 | 0 |
|
|
Unit: minutes.
|