Research on Construction Safety Risk Assessment of New Subway Station Close-Attached Undercrossing the Existing Operating Station

Table 4

List of key risk factors.

Second-level indexKey risk factor

A1 Station structureA12 Absolute settlement value of station structure,
A13 Horizontal displacement of the station structure,
A15 Differential settlement of station structure deformation joint,
A16 Crack width of station structure

A2 Track structureA22 Orbital height difference (Vector value),
A24 Transverse elevation difference of track, A25 Void amount of track-bed

A3 Power supply systemA31 Area power outage renovation, A32 Circuit failure

A4 Water supply and drainage systemA41 System blocking, A43 Pipeline damage

A5 Ventilation and signal systemA51 Equipment sampling pass rate,
A53 Equipment failures,
A56 Equipment renewal rate, A57 Equipment pending repair rate

B1 Construction monitoring of existing stationB11 Information monitoring equipment failures,
B12 Accuracy rate of feedback real-time data,
B14 Horizontal and vertical displacement of retaining pile(wall) and top of slop, B16 Axial force of struts, B17 Anchor tension,
B18 Ground settlement, B19 Clearance convergence of shaft support structure,
B110 Monitoring hole of groundwater level

B2 New space enclosing structureB21 Survey spot arrangement spacing,
B23 Lateral displacement of space enclosing structure

B3Engineering dewateringB31 Stratum filtering flow, B33 Sand content control

B4 Foundation pit excavationB42 Foundation pit excavation plan, B44 Depth of foundation pit

B5 Surrounding rock and soil mass and surrounding environmentB51 Design of station structure,
B52 Stratum and geological condition, B53 Site classification,
B54 Soil liquefaction grade, B55 Buried depth,
B58 Effect of water level reduction on stratum,
B59 Impact of surrounding buildings on construction

B6 Construction technology management of main structureB61Stiffness and deformation reinforcement of main structure,
B62 Stiffness of initial support,
B63 Quality of secondary lining, B65 Mechanical operation,
B66 Construction personnel management, B67Emergency plan

B7 Green constructionB72 Ground traffic control, B74 Noise control, B75Sewage control,
B76 Light pollution control, B77 Dust control,
B78 Construction trash control, B79 Impact on business climate