Intelligent Prediction of the Construction Cost of Substation Projects Using Support Vector Machine Optimized by Particle Swarm Optimization

Table 2

Cost data of the power substation construction (2017).

Serial numberUnit capacity cost (USD/kVA)Serial numberUnit capacity cost (USD/kVA)Serial numberUnit capacity cost (USD/kVA)

140.952370.184550.71
245.532449.894654.09
370.292551.754733.88
452.922632.264833.83
551.462758.914951.76
646.662847.275055.88
740.872929.725157.94
857.173049.345260.41
952.133151.655348.81
1058.043249.115441.79
1156.903351.925566.13
1253.073473.195657.11
1353.503544.545760.17
1464.043653.665851.46
1559.713750.995956.80
1650.293850.016057.42
1761.423952.096151.32
1854.314040.086247.37
1962.834148.726335.63
2060.524236.826453.24
2150.794354.616546.90
2243.224455.41ā€‰ā€‰