A Hybrid Approach for Project Crashing Optimization Strategy with Risk Consideration: A Case Study for an EPC Project

Table 6

Optimum project duration and crash plan in case of most likely time.

NodeStart time
(days)
ActivityCrash time
(days)
Crash cost
(USD)
Project crash cost
(USD)
Project delay penalty cost
(USD)

10A00306,0000
2119B22121,000
3214C1667,000
4287D00
5360E00
6432G00
7524H00
8596I18118,000
9976