Research Article
A Hybrid Approach for Project Crashing Optimization Strategy with Risk Consideration: A Case Study for an EPC Project
Table 6
Optimum project duration and crash plan in case of most likely time.
| Node | Start time (days) | Activity | Crash time (days) | Crash cost (USD) | Project crash cost (USD) | Project delay penalty cost (USD) |
| 1 | 0 | A | 0 | 0 | 306,000 | 0 | 2 | 119 | B | 22 | 121,000 | 3 | 214 | C | 16 | 67,000 | 4 | 287 | D | 0 | 0 | 5 | 360 | E | 0 | 0 | 6 | 432 | G | 0 | 0 | 7 | 524 | H | 0 | 0 | 8 | 596 | I | 18 | 118,000 | 9 | 976 | | | |
|
|