The Intelligence of Octagonal Fuzzy Number to Determine the Fuzzy Critical Path: A New Ranking Method

Table 6

Total float of each activity in the fuzzy project network.

ActivityFuzzy activity time Total float

1-2 (2, 3, 4, 5, 5, 6, 7, 7) (0, 0, 0, 0, 7, 13, 19, 25)
1-3 (4, 4, 5, 6, 7, 7, 8, 9) (0, 0, 0, 0, 3, 9, 16, 21)
1-5 (3, 4, 4, 5, 6, 6, 7, 8) (0, 0, 6, 10, 15, 20, 25, 30)
2-4 (5, 5, 6, 7, 8, 8, 9, 10) (0, 0, 0, 4, 8, 14, 21, 28)
2-5 (6, 7, 7, 8, 9, 10, 11, 12) (0, 0, 0, 0, 7, 13, 19, 25)
3-5 (8, 9, 10, 11, 12, 14, 15, 16) (0, 0, 0, 0, 3, 9, 16, 21)
3-6 (6, 7, 8, 9, 10, 11, 12, 13) (0, 0, 0, 0, 4, 10, 17, 22)
4-7 (10, 12, 14, 15, 15, 16, 18, 20) (0, 0, 0, 4, 8, 14, 21, 28)
5-7 (12, 12, 14, 15, 16, 17, 18, 20) (0, 0, 0, 0, 3, 9, 16, 21)
6-7 (13, 13, 15, 16, 17, 18, 19, 20) (0, 0, 0, 0, 4, 10, 17, 22)