Research Article

RELAP5/MOD3.3 Code Validation with Plant Abnormal Event

Table 2

Initial conditions for reactor trip transient.

VariablesUnitMeasured Measured Design Calculated Calculated Calculated
(average)( second)accuracy( seconds)( seconds)( second)

Pressurizer pressureMPa15.4815.48± 0.37 %15.5215.5115.52
SG 1 pressureMPa6.426.42± 0.37 %6.596.436.47
SG 2 pressureMPa6.406.40± 0.37 %6.576.426.45
Feedwater 1 mass flow ratekg/s499.0504.0± 0.38 %495.2495.4495.5
Feedwater 2 mass flow ratekg/s503.6500.6± 0.38 %497.7498.1498.1
Main steamline 1 mass flowratekg/s493.9492.6± 0.46 %495.2495.4495.4
Main steamline 2 mass flowratekg/s501.6501.5± 0.46 %497.8498.1498.1
Pressurizer liquid level%53.0252.95± 0.37 %56.1051.8852.63
Steam generator 1 NR level%69.2569.15± 0.37 %69.3469.2669.28
Steam generator 2 NR level%69.0669.40± 0.37 %69.3469.2569.28
Nuclear power%91.7291.94± 0.26 %91.6391.7891.77
Cold leg 1 temperatureK559.41559.36± 0.29 %560.74559.15559.51
Cold leg 2 temperatureK559.57559.53± 0.29 %560.59558.99559.35
Hot leg 1 temperatureK593.92593.73± 0.29 %594.64593.23593.55
Hot leg 2 temperatureK594.58594.62± 0.29 %594.64593.23593.55
Average RCS 1 temperatureK576.63576.52± 0.32 %577.69576.19576.53
Average RCS 2 temperatureK577.05577.05± 0.32 %577.62576.11576.45
Programed TavgK576.90576.90± 0.39 %576.97576.97577.00