The Fukushima Event: The Outline and the Technological Background
Table 9
Summary of background for the Fukushima Daiichi accident.
| No. | Topic* | EHP | Notes |
| 1 | External PIE features | YES | Feedback from monitoring of natural events. | 2 | DSA: SBO and LOOP analyses | — | Notes at rows 6 and 7 apply. | 3 | LOOP mitigation effort | YES | Promptly bringing additional DG to the site**. | 4 | SFP loss of cooling | YES | Light pumping device sufficient**. | 5 | PSA: PIE and DG reliability | YES | Failure in estimating DG reliability under tsunami (and aging). | 6 | PSA: core and containment failure | — | Core melt “expected”. | 7 | PSA: SFP failure | — | SFP fuel failure “expected”. | 8 | The licensing | YES | Aging and integrated individual NPP to be better considered. |
|
|
*Topics (1) to (8) are listed in a synthetic way. **Operators or managers from the Fukushima Utility.
|