Research Article
Design of the VISTA-ITL Test Facility for an Integral Type Reactor of SMART and a Post-Test Simulation of a SBLOCA Test
Table 2
Test matrix of the VISTA-ITL program.
| Test type | Test ID | Date | Objectives |
|
SBLOCA phase I | SB-SIS-06 | December 2010 | Safety injection system (SIS) line break SBLOCA and RCP discharge | SB-SCS-01 | December 2010 | Shutdown cooling system (SCS) line break SBLOCA and RCP suction | SB-PSV-01 | December 2010 | Pressurizer safety valve (PSV) line break SBLOCA and pressurizer top |
|
PRHRS performance | PRHRS-SS-N1 | April 2011 | PRHRS actuation during the steady state operation with 100% power | PRHRS-SS-N2 | April 2011 | PRHRS actuation during the steady state operation with 20% power | PRHRS-SS-N3 | April 2011 | PRHRS actuation during the steady state operation under hot standby condition | PRHRS-TR-A3 | May 2011 | PRHRS actuation during the transient operation of SBLOCA |
|
Complete loss of RCS flow rate | CLOF-01 | July 2011 | Complete loss of RCS flow rate | CLOF-02 | July 2011 | Complete loss of RCS flow rate (repetition) |
|
SBLOCA phase II (after hardware modification) | SB-SIS-07 | April 2011 | Safety injection system (SIS) line break SBLOCA and RCP discharge (repetition) | SB-SCS-04 | November 2011 | Shutdown Cooling System (SCS) line break SBLOCA and RCP suction (repetition) | SB-PSV-02 | October 2011 | Pressurizer safety valve (PSV) line break SBLOCA and pressurizer top (repetition) |
|
|