Integrated Cost and Schedule Control Systems for Nuclear Power Plant Construction: Leveraging Strategic Advantages to Owners and EPC Firms

Table 3

EVMS implementing objectives and methods.

Objectives (O-)MethodsInfluencing variables

OI: integrating performance measuresOI1: cost, time, and quality
OI2: life cycle (planning, EPC, start-up, and operation)
OI3: hierarchical schedules
VO1
VO2
VB4
VD4
VP1
VM2
VS-
(Table 2)
OO: enhancing organizational capabilityOO1: planning capability as owner
OO2: project management capability as an EPC
OO3: organizational learning mechanism
OW: optimizing EVMS workloadOW1: minimized additional data requirements
OW2: balanced data linkage and segment
OW3: maximized data utilization for analyses
OC: augmenting cost engineeringOC1: redesigning risk and cost management system
OC2: focused on cost engineering, not accounting
OC3: systemized project baseline