Integrated Cost and Schedule Control Systems for Nuclear Power Plant Construction: Leveraging Strategic Advantages to Owners and EPC Firms
Table 3
EVMS implementing objectives and methods.
| Objectives (O-) | Methods | Influencing variables |
| OI: integrating performance measures | OI1: cost, time, and quality OI2: life cycle (planning, EPC, start-up, and operation) OI3: hierarchical schedules |
VO1 VO2 VB4 VD4 VP1 VM2 VS- (Table 2) | OO: enhancing organizational capability | OO1: planning capability as owner OO2: project management capability as an EPC OO3: organizational learning mechanism | OW: optimizing EVMS workload | OW1: minimized additional data requirements OW2: balanced data linkage and segment OW3: maximized data utilization for analyses | OC: augmenting cost engineering | OC1: redesigning risk and cost management system OC2: focused on cost engineering, not accounting OC3: systemized project baseline |
|
|