Integrated Cost and Schedule Control Systems for Nuclear Power Plant Construction: Leveraging Strategic Advantages to Owners and EPC Firms

Table 6

NPP EVMS standard procedures for system development.

Description
(S-)
Method and procedureTechnique

Budget
(SB)
SBD: standard estimate database
SBE: project estimate
SBB: project budget
(i) Knowledge embedding
(ii) Self-evolving 
(iii) Future extension to BIM

PV
(SP)
SPA: top-down Qty based assignment
SPW: standard weighted milestones
(i) Earned standards
(ii) Simplified resources

EV
(SE)
SEV: rolling up EVs based on Qty
SES: existing scheduling system
(i) Target progress concept
(ii) Activities not connected to cost

AC
(SA)
SAC: decomposed cost from ERP
SAA: existing accounting system (ERP)
(i) Quantity and resource related
(ii) Generic accounting system