Field Tests to Investigate the Penetration Rate of Piles Driven by Vibratory Installation

Table 4

Summary of field tests.

SeriesTest sitePile typePile length (m)ClutchDriving system OperatorPenetration time (s)

A1#Larssen-IV3Without EX450Skilled10.48
B1#Larssen-IV6Without EX450Skilled14.08
C1#Larssen-IV9Without EX450Skilled19.37
D1#Larssen-IV12Without EX450Skilled44.36
F1#Larssen-V9Without EX450Skilled23.12
G1#Larssen-III9Without EX450Skilled18.59
H1#Larssen-IV9With EX450Skilled37.46
J2#Larssen-IV12WithoutEX450Skilled34.26
K2#Larssen-IV12WithoutEX470Skilled28.72
L2#Larssen-IV12WithoutEX450New40.22
Q3#Larssen-IV12WithoutEX450Skilled479.41
R3#Larssen-IV12WithoutEX470Skilled644.11
S3#Larssen-IV12WithoutFree-hangingSkilled672.41