Real-Time Safety Risk Assessment Based on a Real-Time Location System for Hydropower Construction Sites
Table 4
Parameters for the safety risk assessment.
| Item | Cost/reduction value ((N, D, V)/(C, A, M)) | Distance for very dangerous/controlled | Distance for dangerous/affected | Distance for normal/missed |
| Critical edge | (0, 4, 8) | <1 m | 1 m-2 m | >2 m | Concrete vibrator | (0, 5, 10) | <3 m | 3 m–5 m | >5 m | Concrete paver | (0, 5, 10) | <3 m | 3 m–5 m | >5 m | Safety supervisor | (0.5, 0.8, 1) | <5 m | 5 m–10 m | >10 m |
|
|