Key Techniques and Risk Management for the Application of the Pile-Beam-Arch (PBA) Excavation Method: A Case Study of the Zhongjie Subway Station

Table 3

Management critical value for settlement of ground surface and building.

Construction stepSurface settlementBuilding settlementsHorizontal convergenceCrown settlement
AbsoluteDifferential

Pilot heading excavation80251050
Supporting arch 351020
Main structure25515
Summation (mm)140400.002 1570

denotes the length of the existing building in the direction perpendicular to the tunnel axis.