[Retracted] An Improved Ant Colony Optimization Approach for Optimization of Process Planning
Table 6
Precedence constraints for Part 2.
Features
Operation
Precedence constraints description
Hard or soft
F1
Milling (OP1)
F1 (OP1) is the datum and supporting face for the part; hence it is machined prior to all features and operations.
Hard
F2
Milling (OP2)
F2 (OP1) is prior to F10 (OP12, OP13, and OP14) and F11 (OP15, OP16) for the material removal interactions.
Hard
F5
Milling (OP5)
F5(OP5) is prior to F4 (OP4) and F7(OP7) for the datum interactions
Hard
F6
Milling (OP6)
F6 (OP6) is prior to F10 (OP12, OP13, and OP14) for the datum interaction.
Hard
F7
Milling (OP7)
F7 (OP7) is prior to F8 (OP8, OP9, and OP10) for the datum interactions.
Hard
F8
Drilling (OP8)
OP8 is prior to OP9 and OP10; OP9 is prior to OP10 for the fixed order of machining operations.
Hard
Reaming ()
Boring (OP10)
F9
Milling (OP11)
F9 (OP11) is prior to F10 (OP12, OP13, and OP14) for the datum interaction
Hard
F10
Drilling (OP12)
OP12 is prior to OP13 and OP14; OP13 is prior to OP14 for the fixed order of machining operations. F10 (OP12, OP13, and OP14) is prior to F11 (OP15, OP16), and OP12 of F10 is prior to F14 (OP19, OP20) for the datum interaction.
Hard
Reaming (OP13)
Boring (OP14)
F11
Drilling (OP15)
OP15 is prior to OP16 for the fixed order of operations.
Hard
Tapping (OP16)
F13
Milling (OP18)
F13 (OP18) is prior to F4 (OP4) and F12 (OP17) for the material removal interaction.
Soft
F14
Reaming (OP19)
OP19 is prior to OP20 for the fixed order of machining operations.