Heuristics for Multiobjective Optimization of Two-Sided Assembly Line Systems
Table 6
Allocation of tasks for 9th assignment of P19 (CT = 6 min).
| W/S type | Allotted tasks | Processing time for task “” | Work load at each station | Idle time at each station |
| W/S(L)-1 | 1 3 | 2.80 2.50 | 5.30 | 0.70 | W/S(R)-1 | 2 | 3.10 | 3.10 | 2.90 | W/S(L)-2 | — | — | — | — | W/S(R)-2 | 4 | 3.40 | 3.40 | 2.60 | W/S(L)-3 | 8 6 | 3.30 2.70 | 6.00 | 0.00 | W/S(R)-3 | — | — | — | — | W/S(L)-4 | 5 7 | 3.20 2.60 | 5.80 | 0.20 | W/S(R)-4 | — | — | — | — | W/S(L)-5 | 9 | 5.90 | 5.90 | 0.10 | W/S(R)-5 | 10 13 | 3.70 1.80 | 5.50 | 0.50 | W/S(L)-6 | 11 | 4.10 | 4.10 | 1.90 | W/S(R)-6 | — | — | — | — | W/S(L)-7 | 12 16 | 2.20 2.40 | 4.60 | 1.40 | W/S(R)-7 | 15 14 | 2.30 1.20 | 3.50 | 2.50 | W/S(L)-8 | — | — | — | — | W/S(R)-8 | 17 | 5.80 | 5.80 | 0.20 | W/S(L)-9 | 18 19 | 3.80 2.10 | 5.90 | 0.10 | W/S(R)-9 | — | — | — | — |
|
|