Research Article

An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation

Figure 3

Construction procedure of the building example. 1: clear lot and excavate for foundation; 2: erect formwork for foundation concrete; 3: install foundation reinforcing; 4: pour footings; 5: build foundation block; 6: refill foundation earth; 7: erect formwork for 1st story; 8: install reinforcing for 1st story; 9: pour columns, beam, and slabs for 1st story; 10: build block in 1st story; 11: erect formwork for 2nd story; 12: install reinforcing for 2nd story; 13: pour columns, beam, and slabs for 2nd story; 14: build block in 2nd story; 15: erect formwork for 3rd story; 16: install reinforcing for 3rd story; 17: pour columns, beam, and slabs for 3rd story; 18: build block in 3rd story; 19: install heat insulation in the roof; 20: install waterproof layers for the roof.
673248.fig.003