Research Article

Integrated Project Scheduling and Staff Assignment with Controllable Processing Times

Table 1

Names for the integrated problem.

ReferenceName used for the integrated problem

Bellenguez and Néron [14], Bellenguez-Morineau and N ron [15]Multiskill project scheduling problem
Brucker and Knust [16], Drezet and Billaut [17]Project scheduling with labor constraints
Vairaktarakis [18]Resource-constrained job assignment problem
Valls et al. [19]Skilled workforce project scheduling
Corominas et al. [20]Problem of assigning and scheduling a set of tasks to a set of workers
Drexl [21]Scheduling of project networks by job assignment
Dodin and Elimam [22]Problem of audit staff scheduling
Heimerl and Kolisch [23], Kolisch and Heimerl [24], Gutjahr et al. [25], and Gutjahr et al. [26]Project scheduling and staffing