Abstract

Depletion of fossil fuel and the inability to meet the rising demand of electricity are some drawbacks for the economic development of Bangladesh. Carbon emission done by developed world is also troubling the country. This paper focuses on the potential of micro-hydropower plant in Bangladesh due to its numerous rivers and canals providing off-grid power to the remote areas and also to the areas that are still outside the main grid network. This paper reflects on the current energy scenario in Bangladesh, the need to explore green energy thus proving how the establishment of widespread micro-hydropower plant can help overcome the current power crisis and play a role in the economic progress of the country. The existing potential sites are mentioned and the means to identify new sites are outlined by performing hydrology studies, topographic studies, head calculations, turbine selection, and so forth.

1. Introduction

Bangladesh, with its emerging commerce and industries, is facing a daunting task to cope up with the power crisis. There is a lack of sufficient power generation capacity, and the existing national grid network is unable to power the whole nation. The rural and remote areas have a low-load demand but the electricity supply has been characterized by high transmission and distribution costs, transmission losses, and heavily subsidized pricing. The demand for power is increasing at a rapid pace although the generation of power has not increased at the same proportion. The gap between demand and supply of power is quite significant. The shortage of power generation capacity is estimated to be around 2500 MW [1]. As a result, lack of a reliable electricity service has deterred foreign investment and held back economic growth. Energy consumption per capita is only 154 KWhr which is much less than any of the developed countries [2]. In order to overcome the heavy power crisis and rapid depletion of available resources, Bangladesh needs to opt for alternate energy sources in the form of fossil fuels and renewable energy sources. The roadmap to energy security and energy sustainability will be achieved only if the economic and environmental aspects are taken into consideration.

Due to the huge contribution of 19% of the world’s electricity power from both large and small power plants, hydro power is the most widely used renewable energy [35]. Department of Energy (DOE) defines large hydropower as power plants having generation capacity of more than 30 MW [6]. Small hydropower plants are termed as having a generation capacity of 100 KW to 30 MW [6]. Micro-hydropower plants are defined as having a generation capacity ranges from 5 KW to 100 KW [4]. Water heads of 2 meters can be suitable to generate power efficiently with proper implementation of advanced technology. The energy problems in remote and hilly areas exist due to the uneconomical planning of the grid network [3, 4]. Micro-hydropower provides low-cost solution for these remote sites. It provides a good solution for energy problems in remote and hilly areas where the extension of grid system is comparatively uneconomical [7].

In this paper, we have explored the potential of micro-hydropower plant as a source of renewable energy in order to tackle the power crisis of Bangladesh with in-depth analysis of Bamerchara micro-hydropower unit as a model. Section 2 deals with the complete energy scenario in Bangladesh, Section 3 explains the necessity of exploration of alternative sources other than fossil fuel, Section 4 describes micro hydro as a source of green power generation, Section 5 demonstrates the parameters needed to be considered to explore new potential sites for micro-hydropower generation, Section 6 explains the economic considerations, Section 7 shows the potential micro-hydrosites already identified, Section 8 describes the socioeconomic impacts due to the establishment of micro-hydropower plant and economic feasibility of installing these plants, and Section 9 draws the conclusion.

2. Energy Scenario in BD

The main sources of power generation are hydropower, biofuels, coal, and natural gas. Large-scale hydropower (>40 MW) generation has been established which leads to resettlements thus losing agricultural lands. The nation has a high dependency on natural gas and hydropower for electricity generation but, as mentioned previously, low per capita energy consumption. The reserve for these fossil fuels is depleting at a high rate. At present the country does not have any energy security, and this is why after the fossil fuels are completely consumed, the country will face severe energy crisis. That is a huge concern for the mass people of the country. On the other hand, the country is seriously affected by the natural calamities. Thus, energy sustainability is another important aspect that should be taken into consideration. All these factors lead to the inability to consider energy sustainability. Generating more power from fossil fuels to overcome the gap between demand and supply has made it even more difficult to attain energy sustainability due to their high depletion rate. As a result, the circumstances are such that alternative energy sources other than fossil fuels should be taken into consideration to have a secured and sustainable energy future.

The current reserves for fossil fuels in Bangladesh should be analyzed. Bangladesh has modest hydrocarbon resources and rich renewable energy sources especially in the form of traditional energy. The Natural gas reserves in Bangladesh are likely to be depleted before 2020 which will bring the power generation at a halt. In Barapukuria, the deposits of Coal may supply about 250 MW [8]. When the demands for electricity would exceed 11000 MW, emergency measures should be taken to conserve energy, to achieve high-efficiency plants, explore gas, and coal reserves to prevent the inevitable disaster due to the lack of power supply. The Government of Bangladesh is planning to tackle the situation by renting power systems and coal-fired systems. But more importantly energy supplies using RETs must be developed and utilized.

To fulfill the demands as estimated for 2020, power generation should be increased and government is providing the following incentives as mentioned in the Renewable Energy Policy 2008 and Government initiatives on RET 2009 [9].(i)First are the policy sets targets for developing renewable energy resources to meet five percent of the total power demand by 2015 and ten percent by 2020.(ii)Second is creating enabling environment and legal support to encourage the use of renewable energy.(iii)Third is implementing policies for mitigation of environmental issues arising out of use of renewable energy.(iv)Fourth is processing of grid-connected renewable energy projects.(v)Electricity generated from renewable energy projects, both in public and private sectors, may be purchased by power utilities or any consumer through mutual agreement (up to 5 MW).(vi)To promote renewable energy in power sector, all renewable energy equipments and related raw materials in producing renewable energy equipments will be exempted from charging 15% VAT.(vii)Bangladesh Bank has sanctioned a revolving fund of 200 Crore Tk. for renewable energy projects.(viii)In addition to commercial lending, a network of microcredit support system will be established especially in rural and remote areas to provide financial support for purchases of renewable energy equipment.

3. Necessity of Exploration of Alternative Sources Other than Fossil Fuel

Bangladesh has very minimal contribution to global warming in comparison with many other developed countries. Bangladesh shares less than 0.1% of global emissions of CO2 compared with 24% of the USA and emits about 0.19 tons of CO2 per capita [1]. Major areas of emissions are the industries and power plants. In the rural areas burning of wood, dung, and crop residues causes air pollution and results in severe health problems considerably for women working indoors. These pollution and emissions lead to environmental degradation which in turn causes increased climate risks and natural disasters.

Although fossil and biofuels contribute to such pollution, there has been recent information that Bangladesh has over 2 billion of low-sulphur content coal reserves. Also there are reserves for natural gas and oil, where oil reserves are estimated to be 56.9 million barrels [10]. More initiatives to explore such reserves should be taken but unfortunately the economic potential and efficient use of these resources are limited due to lack of exploitation and distribution facilities. The large reserves of oil are present in Bangladesh but still 90% of its oil demands are met through imports [8]. For the exploration and exploitation of these resources, required funds and technologies are highly insufficient. Foreign intervention is always not profitable in terms of economic and environmental aspects. Leakage and other accidents in the past in such reserves have created a suspicion for their acceptability. Taking into consideration the economic and environmental issues related to fossil and biofuel reserves, it is quite obvious that a more feasible alternative should be sought.

Renewable energy sources are abundant in Bangladesh. Already some of them have been implemented and some are yet to be tried. 3.6 GW of electricity is generated annually, 6% comes from large-scale hydropower, and the remaining 94% comes from thermal (natural gas and oil-fired) [1]. Further exploitation of hydropower is expected to be limited to small and mini-hydropower plants due to the flat terrain and numerous canals with estimated potential of about 250 MW [8]. Biomass, solar, wind, and micro-hydropower plants are some other potential sources of renewable energy. Most of the developing countries are taking into consideration environment friendly alternatives and in context Bangladesh government has allocated 20% of total public sector investment on energy sector in their last budget along with other incentives as mentioned previously [9]. It is of utmost importance that alternative sources of energy are explored. It has been already mentioned that the factors governing this emergency need include dependency on fossil fuels, depletion of reserves, limitation on exploiting new reserves, and economic and environmental impacts.

4. Micro-Hydro as a Source of Green Power Generation

Micro-hydropower in comparison to other nonconventional energy sources includes the following.

(a) Selection of Potential Sites
Hilly areas with natural water falls on the dam-toe or canal drops are suitable sites for micro-hydropower plants. For such site selection long range studies are not required. Sites for biomass plants are usually located by taking into consideration the availability of water, raw materials for biogas generation, free open space, total space required, minimum gradient, water table, distance from wells, and grid. Wind power plants are situated at a certain place where wind velocities are very high and relatively constant all over the year. Monthly and annual average velocities should be similar year in year out. Suitable locations for solar power plants are areas consisting of flat terrain with no high raised buildings and trees nearby [11].

(b) Problems while Connecting to the National Grid
Micro-hydropower plants produce nearly constant input power. The only variation results in change of seasons due to the seasonal climate changes and water flow rate. So overall for a certain season, the power is almost constant. The power fed to the main national grid network is very smooth with no such nonlinearities that are present in other sources of energy. Power fed to the grid produced by solar and wind energy consists of fluctuations on voltage and frequency levels, harmonic distortion, nonlinearities, and other abnormalities. This usually occurs due to the variation in wind velocities and solar light intensity all throughout the day. In numerous occasions the power needs to be put off grid because of certain factors going below the threshold level during power transmission and distribution [11].

(c) Problems Governing Operation, Maintenance, and Control
Micro-hydropower is easy to operate and there is no need for rigorous maintenance, whereas wind power plant causes severe noise pollution, teething troubles, and poor performance due to operation and maintenance problems. Major challenge relies on designing signal conditioner, computer interfacing, and software for system operation. The pulsating input power pattern for the wind power station is another major problem. Moreover, there are various problems while handling biogas: pollutants such as effluent slurry, accumulation of volatile fatty acids, gas forming methanogenic bacteria, and leakage of gas from gas holder. Other problems include drop in Ph level and failure of digester [11].

(d) Affects on the Environment
Micro-hydropower, wind, and solar power plants are clean and pollution free. They are basically very environment friendly sources. Although wind power plants create noise pollution, biomass causes environmental pollution and it does not meet the pollution control regulation, whereas micro-hydropower maintains the ecological balance and stream flow of the rivers. The impacts on the environment of each energy sources have been studied thoroughly and the enhancement of these technologies has been considered [11].
The estimated power output is governed by the following equation: 𝑃=𝑄×𝐻×7.83, where P is the theoretical amount of power in KW, Q is the discharge flow rate in m3/s and H is the water head in metres. The equation is an approximation relied on theoretical studies. The actual power output varies depending upon pressure losses through the inlet and penstock also upon the turbine and generator efficiency. Another factor is the reduction of stream flow leading to the penstock due to environmental and fisheries constraints. The factors mentioned reduce the amount of energy produced.
The aforementioned comparison shows that micro-hydropower is a potential source of energy. Full utilization of this energy will result in environmental friendly generation of power from canals and rivers.
Micro-hydropower projects have been successfully implemented to provide standardized technologies for off-grid decentralized power to these remote hilly areas and small villages. Power to some mountainous villages has brought about major socioeconomic development. Micro-hydropowers have replaced diesel generators and implemented in a hybrid system in line with solar power [11]. These power plants have been used for direct mechanical energy for small industries and agriculture. Small-scale projects include battery charging, welding workshop, crop processing, grain milling, home, farm, ranch, and village. Another small-scale implementation may be to power homes in remote areas without a dam. The most significant use of micro hydropower is the off-grid decentralization of its surrounding areas. Micro-hydropower meets smooth and stable power supply. Thus, the surrounding areas of individual generating stations can be easily powered and it is very economical. This will reduce consumer demand on the national grid network. Moreover, micro-hydropower stations can always be fed to the national grid. Micro-hydropower projects are generally considered to be more environmental friendly than both large hydro and fossil fuel-powered plants. With all these advantages, micro-hydropower can be implemented as principle renewable sources for sustainable development especially in developing countries like Bangladesh.

5. Parameters Needed to Be Considered to Explore New Potential Sites

5.1. Choosing a Micro-Hydrosite

Micro-hydropower sites should be chosen by taking into consideration the terrain and availability of high stream flow rate. Micro-hydropower plants are to be situated in hilly areas where there are natural falls, on the canal drops or at the dam-toe. As mentioned before long range studies are not required for such site selection. Many people need electricity in places that are beyond the reach of power lines. Some even look at the creek that flows through their property, tapping the energy of the water either for their own use or to sell to potential buyers. Regardless of the reason for wanting to develop a micro-hydroproject, an appropriate location is required for the project. Choosing a site is one of the most important steps in development, as it will largely determine the amount of energy that can be developed and the complexity of site development. Some factors to be considered are outlined as follows [12].

5.1.1. Topographic Maps

Mapping of an area is one of the prime tools for site selection. Information such as the length of pipelines, transmission lines, and possible water head can be obtained from such maps. Other relevant information is the source of the stream and its direction of flow, roads to access the site, and also the size of the drainage area. Some of the sources for mapping include the 1 : 50,000 scale national topographic system (NTS) maps, 1 : 20,000 scale TRIM maps, local forestry maps, and custom maps based on recent photos. Mapping of the possible regions provides detailed accuracy for site feasibility with increase in cost.

5.1.2. Site Hydrology

Hydrology study includes exploration of the origin of the stream flow and its destination. It also includes measurement of stream flow direction and flow rate. Although this study is time consuming, but it facilitates proper planning. The available tools to determine the hydrology of a potential site include maps, stream flow data, and water quality studies.

5.1.3. Water Quality Studies

Studies should be performed to obtain relevant data regarding the level and variety of sediments like silt, fine sand, gravel, rocks, floating debris, and dissolved chemicals. Basically the data are used to determine the material for the equipment that comes in contact with water and also to take necessary precautions for the sediments that flow along the stream. There are other hydrological matters related to water quality studies that need to be considered.

5.1.4. High Head

The water should be allowed the maximum vertical displacement and the shortest path to travel. The maximum vertical displacement accounts for the high water head. Large water head accounts for higher power produced. For high head, the turbine speed will be large; thus a small turbine can be opted for a given power output. However, at high heads the pipe pressure ratings and the strength of the pipe materials should be considered for design. Water must be allowed in the shortest route to travel; otherwise it will require long penstock which is quite costly. Longer pathway for the water to travel will reduce its flow rate due to fluid and other forms of friction.

5.1.5. Lines or Load Should Be at a Close Proximity

For on-grid generation, the site should be closer to the distribution and transmission line. Also for off-grid generation, the loads should be at a close proximity. This ease in distributing the power will result in low transmission costs. It is to be noted that for on-grid micro-hydroplant it is cost effective to connect to the 11 to 33 KV lines. Voltage levels greater than that increase the connection the cost.

5.1.6. Turbine

The selection of type of turbine is one of the problems in design of hydroplant. The characteristics, parameters, and classification involved facilitate the choice of turbine. There are two methods of selection [6].

(1) Graphical Selection
It is the various types of turbine, graphs relating discharges, head work, model test result, and test report. Turbine is selected according to the head and discharge values [6].

(2) Analytical Selection
According to the head and discharge values, the turbine parameters are calculated using the formula 𝑃𝑡=𝑃𝜂,(1) where P is power in KW, and η is the system efficiency including turbine, generator, and gear box efficiency.

Then specific speed can be calculated as 𝑁𝑠=(𝑁×𝑃𝑡)0.5𝐻54,(2) where 𝑃𝑡 is turbine output in KW, and N is the rated speed in rpm.

Runner Diameter
After performing model test and selecting design of turbine, the actual runner diameter is determined by the manufacturer. The following formula can be used [6]: 𝐷𝑟=0.0242𝑁𝑠(2/3),(3) where 𝐷𝑟 is runner diameter, and 𝑁𝑠 is specific speed in rpm 𝐷2=84.6×𝐷𝑟×𝐻0.5𝑁,(4) where 𝐷2 is Discharge diameter and N is speed of turbine. Turbines can be classified according to their specific speed:(1)high head turbine and low specific speed (Pelton),(2)medium head turbine and medium specific speed (Francis),(3)low head turbine and high specific speed (Kaplan and Propeller). Turbines are designed as Dam Base, Canal fall, Run-off River, and Hilly region depending upon specific site conditions [11].

Kaplan Turbine
Large quantity of water at low head is suitable for such turbines. These turbines range from head of 30 metre and specific speed from 255 to 860 (Power in KW) [13].

Francis Turbine
Moderate quantity of water at medium head is suitable for such turbines. These turbines range from head of 55 metre to 240 metre and then specific speed from 51 to 255 (Power in KW) [13].

Pelton Turbine
These turbines range from 8.5 to 30 (Power in KW) for single jet Pelton Wheel and from 30 to 51 (Power in KW) for Pelton Wheel with double jet. The head value ranges above 240 metre [13].

Bulb Turbine
Large rivers with high flow are suitable for such turbines. These are more economic than Kaplan turbine. These turbines range from head of 3 to 23 metres and specific speed from 200 to 40 (Power in KW) [13].

PIT Turbine
These are modified version of the Kaplan turbine that works on head value below 15 metre [13].

S-Type Turbine
These turbines are smaller version of Kaplan turbine with horizontal inlet. These turbines have water head as low as 1 metre to 15 metre. Specific speed ranges from 50 to 500 (Power in KW) [13].

Cross-Flow Turbine
These turbines are subset of impulse turbine. The hand ranges lower than Pelton turbine with values up to 180 metre and specific speed up to 2 MW [13].

Penstock Diameter
The diameter is calculated using design discharge, head, and plant capacity using this formula [6]: Π×𝐷24=𝑄𝑑𝑉.(5) This formula gives the diameter of penstock [13].

5.2. Generators

The micro-hydropower can be installed with induction generator and synchronous generator. For both on-grid and off-grid modes induction generator gives advantages such as low cost and robust construction. However, synchronous generator is used in off-grid mode.

Synchronous Generator
Generally for commercial purpose synchronous machine is widely used. Generators driven at low speeds by prime-movers like water turbines will have salient pole construction having large number of projected poles [13].

Induction Generator
This needs very little auxiliary equipment and can be run in parallel with generator without hunting at any frequency. For IG speed variation of prime-mover is less important. Power fed to the grid varies from 0.94 to 0.97 p.u. due to variation in line losses while the generator output almost remains constant. With the terminal capacitors, there is marginal increase in power fed to the grid resulting in improved efficiency [13].

Low Environmental Impact
When choosing the site, care must be taken to avoid unacceptably high environmental impacts such as damage to fish populations, endangered species, or air quality [13].

Power Reliability
The Power output is directly dependent upon head and discharge. Head and discharge depend upon rainfall and also stream flow in rivers and canals. The estimation of river flow and rainfall determines the reliability of Power output from the micro hydro-powerplant [13].

6. Economic Considerations

6.1. Economic Feasibility

There are some donor agencies or global financial institutions which contribute for green technology and reduction of carbon emission. Green technology fund can be obtained from World Bank Climate Investment Funds [14], The Least Developed Countries Fund (LDCF) [14], and The Adaptation Fund. Besides these available funds, there are also some internationally recognized mechanisms, which create opportunity for developing nations to generate funds for implementing any green project in their country. Two of such mechanisms are CDM (Clean development mechanism) and Carbon finance. The Clean Technology Fund is a climate fund that will aim to promote low-carbon economies by helping to finance deployment in developing countries of commercially available cleaner energy technologies through investments in support of credible national mitigation plans that include low-carbon objectives. The Strategic Climate Fund will help more vulnerable countries develop climate-resilient economies and take actions to prevent deforestation. The Least Developed Countries Fund (LDCF) was established under the United Nations Framework Convention on Climate Change (UNFCCC) at it seventh session in Marrakech and is managed by the Global Environment Facility. The fund addresses the special needs of the 48 Least Developed Countries (LDCs), which are especially vulnerable to the adverse impacts of climate change. The Adaptation Fund has been established by the Parties to the Kyoto Protocol of the UN Framework Convention on Climate Change to finance concrete adaptation projects and programmes in developing countries that are Parties to the Kyoto Protocol.

The CDM (Clean development mechanism) allows emission-reduction (or emission removal) projects in developing countries to earn certified emission reduction (CER) credits, each equivalent to one ton of CO2 [15, 16]. These CERs can be traded and sold and used by industrialized countries to meet a part of their emission reduction targets under the Kyoto Protocol. The World Bank Carbon Finance Unit (CFU) uses money contributed by governments and companies in OECD countries to purchase project-based greenhouse gas emission reductions in developing countries and countries with economies in transition [17]. The emission reductions are purchased through one of the CFU’s carbon funds on behalf of the contributor, and within the framework of the Kyoto Protocol’s Clean Development Mechanism (CDM) or Joint Implementation (JI). The role of the Bank’s Carbon Finance Unit is to catalyze a global carbon market that reduces transaction costs, supports sustainable development and reaches, and benefits the poorer communities of the developing world.

As Bangladesh is a developing nation which suffered most for the climate change and COP15 conference which took place in Copenhagen called Bangladesh as most vulnerable country of the world, micro-hydropower project will be encouraged by all quarters in this country and thus Bangladesh will also get funds from all the above mentioned fund raising body.

Estimating the Preliminary Cost
Costs for the micro-hydropower plant project include initial costs related to study conducted for proper site selection and project development; construction expenses regarding design and purchasing of equipments; and annual costs related to maintenance, taxes, rentals, and so forth.

Initial Costs
These include costs for site selection, feasibility studies, environmental impact assessments, permits, obtaining land rights, financing fees, energy purchase agreements, and interconnection agreements.

Feasibility Studies
The purpose of this study is to assess whether to proceed with the project. Feasibility studies involve environmental assessment, hydrology assessment, preliminary designs, and detailed cost estimates.

Construction Costs
These include necessary equipments, civil works, access roads, transmission lines, interconnection fees, and others related to setting up the project.

Services
Costs for the work force required to build the plant. Costs include hiring engineers, managers, and labourers, also providing them other facilities like food, lodging, and so forth.

Costs for Equipments
These include purchasing various equipments like protection system, control system, turbine, generators, and so forth. Also costs include transportation, installation, and maintenance of these equipments.

Annual Costs
These includes operation and maintenance costs for the complete project and include administrative costs such as salaries, rentals, and fees.

7. Micro-Hydrosites in Bangladesh

In February 1981, the Water Development Board and Power Development jointly carried out a study on the assessment of Small/Mini-Hydropower Potential in the country [11]. The committee explored 19 prospective sites for possible installation of small hydropower plants. Later in the month of April 1984, Six Chinese experts visited Bangladesh and they identified 12 potential sites for development of mini-hydropower plant. Out of these sites, only Mahamaya Chara, near Mirersharai, close to Dhaka-Chittagong highway was identified as the best site for development of small hydro. Following are the sites that were identified (Table 1) [9, 11].

In 2004 sustainable Rural Energy, Local government Engineering Department has explored some potential micro-hydrosites in Chittagong which is listed in Table 2.

Most of the potential sites are situated in the Chittagong hill tracts (CHTs). It requires potential utilization of hydropower and indigenous technical knowledge to utilize the existing opportunities in the CHT areas. Decentralization of micro-hydropower units with local implementation and management through self-reliance and the use of local natural resources will have significant impact on the remote tribal rural development.

Mr. Aung Thui Khoin set such an instance by setting up a micro-hydroplant. The unit was constructed with wooden turbine and making an earthen dam on the flowing Hara Khal at remote hilly region of Monjaipara, Bandarban. About 10 kW electricity is being generated by this micro-hydropower unit that has illuminated 40 households of that village. That led to an agreement between LGED and innovator Mr. Aung Thui Khoin for a month long study. The objectives of the study were identification of micro-hydropower potential sites within the hilly regions and promotion of indigenous technologies for development of hydropower. Possible integration with power generation and irrigation schemes was also under consideration.

From the study, some prospective sites for micro-hydropower development in three districts of CHT region were identified with the help of LGED officials, local communities, and head man. The potential sites are given as follows in Table 3.

“Feasibility Study on R&D of Renewable Energy (Solar, Wind, Micro-Mini-Hydro)” has been carried out by the Institute of Fuel Research Development (IFRD) of Bangladesh council of Scientific and Industrial Research (BCSIR). Various data are collected through the related instruments regarding the Micro-Mini-Hydrostudy at two selected places of (1) Shailopropat, Bandarban, and (2) Madhobkundu, Moulibhibazar.

The collected data and information are analyzed on various aspects at RET laboratory of IFRD. On the basis of analysis of collected data up to June 2001, it is expected that 5 to 10 kW capacity Micro-Hydropower plant at Sailipropat, Banderban, and 10 to 20 kW capacity Micro-Hydropower Plant at Madhobkundu, Moulibhibazar, can be installed for electricity generation are given in Table 4.

Bamerchara project is the first demonstration micro-hydropower unit in Bangladesh. This project was initially implemented in order to provide irrigation facilities to 355 ha land. This unit has helped us to get insight knowledge and practical experience in harnessing micro-hydropower. It has enabled the local farmers to use the electricity from that unit for daytime irrigation, so a considerable amount of power is saved. The remaining power could be stored in a battery bank or could be used at grain mills or cooking.

Salient Feature of Bamerchara Micro-Hydropower Unit
Estimated capacity of the system was 10 kW. Salient feature of the unit has been illustrated as follows:(i)turbine type: cross flow,(ii)penstock: 52 m,(iii)design flow: 150 liter/sec,(iv)net head available: 6 m–10 m, (v)preferred governor: flow control (manual), (vi)electrical output: 4–6 KW, 50 Hz, 3 phase voltage, 220 V/440.
Considering water head of 11 meters and flow rate of 150 L/s, it was estimated that maximum 10 kW hydropower could be generated from “Bamerchara” site (Figures 1 and 2). But when irrigation starts, water head falls rapidly. Consequently full power generation was not possible. Furthermore, about 41% potential energy was lost by the penstock, turbine, and generator and transmission line. Figure 3 illustrates relationship between water head and extractable hydropower from a stream.

8. Socio Economic Impact

Bangladesh is mainly an agricultural country. Almost the whole population is dependent upon agriculture either directly or indirectly. Unfortunately, Bangladesh has never enjoyed 100% electrification [9]. As a result irrigation has hampered a great deal due to the power crisis.

In total Bangladesh has 232 rivers including the main rivers and their branches. So, if proper selection criteria are maintained, it will not be very difficult to find the potential sites where runoff MHP plant can be set up. The electricity produced from these sites can play a very vital role in facilitating the local farmers to have proper irrigation facility [18].

Most of the identified places so far are in the hilly areas where mainly the tribal people have their habitat. Currently most of them are out of electrification facility. Exploration of further potential sites and proper utilization of the existing sites will create opportunity to bring them under electrification. Besides improving their standard of life it will enable them to start small-scale industries in those remote areas [19]. Hence, there will be opportunities for jobs and self-employment. It would also encourage them to start home-based industry through the availability of three-phase power [18]. Production of electricity in remote areas will save huge transmission and associated infrastructural cost [18]. Also, these hilly areas being an attractive tourist spot undoubtedly tourism will flourish due to the availability of power. Tourism has also been a good source of revenue for Bangladesh.

Shrimp cultivation is one of the main sources of foreign revenue of the country [20]. But due to shortage of electricity, it has been very difficult to apply the modern techniques of cultivation. Potential river sites with run-off MHP facility will enable the local farmer to apply semi-intensive and intensive method of cultivation.

9. Conclusion

In this paper, the current power crisis of Bangladesh has been discussed. Necessity of exploring energy from alternative sources and impact of micro-hydro as an alternative source has been presented. Since micro-hydropower plant requires terrain and availability of high stream flow rate, so, it has a good potential in the north-eastern hilly regions of Bangladesh which is also evident from the presented data. Due to the abundance of rivers and canals, Bangladesh has a good run-off river micro-hydropotential but it is yet to be explored. Parameters in order to set up new micro-hydroplants have been discussed. A primary guideline of economic feasibility and a way of raising necessary fund have been proposed.

No development strategy can be implemented without power. Bangladesh is still very much dependent on fossil fuel for power generation. But, the country has limited resources which are likely to be finished very soon. On top of that, burning of fossil fuels has very negative environmental consequences. Now-a-days, the whole world is much more concerned than ever before about not only the depletion of various energy resources but also environmental degradation caused by the existing pattern of fossil fuel use. As a populous country with small energy resources, our concern is even greater. Proper consideration of parameters to explore potential sites can also inspire the interested individuals and can work as an incentive to establish micro-hydroplant for local use. Due measures of establishing decentralized small-scale water power or micro-hydroschemes can prove it as an effective eco-friendly source of power generation, as internationally funds for green energy are available that can be a great appreciation for government to explore this option also.