Simulation-Based Fuzzy Logic Approach to Assessing the Effect of Project Quality Management on Construction Performance
Table 8
Durations and project requirements of the activities.
| Activity | Project requirements | Advance rate (min/m) | Distance buffer (m) |
| Excavation | 1 backhoe 1 survey crew | (2.9, 4.2, 6.1) | 20 |
| Detailing excavation | 6 laborers 1 survey crew | (3.1, 4.0, 5.2) | 40 |
| Bedding | 1 loader 2 types of vibratory equipment 6 laborers | (1.9, 3.8, 4.7) | 20 |
| Pipe installation | 1 loader 2 pipeman 1 laborer | (3.2, 4.5, 5.5) | 20 |
| Finishing of bedding | 1 loader 2 types of vibratory equipment 6 laborers | (2.5, 3.9, 5.2) | 40 |
| Backfilling | 1 dozer 1 type of compaction equipment | (2.7, 3.6, 4.8) | ā |
|
|