Simulation-Based Fuzzy Logic Approach to Assessing the Effect of Project Quality Management on Construction Performance
Table 9
Significance of the effect of the PQM practices on the project requirements.
| Project requirements | PQM practices | Significance on project requirements |
| Material supply | Expediting | Medium | Supplier qualification | High | Internal and external examinations | Medium |
| Design information | Change and communication | Medium | Constructability review | Medium | Internal and external examinations | Medium | Expediting | Low | Operability and value review | Low | Personnel qualification and training | High |
| Work conditions | Constructability review | Low | Internal and external examinations | Medium | Personnel qualification and training | High | Risk management | Low | Safety management | High |
|
|