Installed elements in the stochastic scenario-based problem.
| Year | Added elements |
| | 15 MW WF at bus 4 40 MW gas unit at bus 5 35 MW WF at bus 5 70 MW hydro unit at bus 6 50 MW transmission line between buses 4 and 6 | | — | | 60 MW gas unit at bus 5 | | 60 MW gas unit at bus 4 100 MW steam unit at bus 5 | | 60 MW gas unit at bus 1 60 MW gas unit at bus 2 90 MW gas unit at bus 5 |
|
|