Research Article

Site Monitoring and Numerical Modelling of a Trial Embankment's Behaviour on Venice Lagoon Soils

Table 1

Embankment construction and removal phases.

PhaseDateFill height (m)Action

012 September 20020.00reference measurement
112–17 September 20020.5+0.5 m sand
223–26 September 20021.00+0.5 m sand
31–3 October 20021.50+0.5 m sand
49–14 October 20022.00+0.5 sand
57-8 November 20022.50+0.5 sand
613–18 November 20023.00+0.5 sand
727–29 November 20023.50+0.5 sand
816–19 December 20024.00+0.5 sand
930 December 2002–03 January 20034.50+0.5 sand
1014–16 January 20035.00+0.5 sand
1122–25 January 20035.50+0.5 sand
124–7 February 20036.00+0.5 sand
1324–27 February 20036.50+0.5 sand
1406–10 March 20036.70+0.2 gravel
1515–29 June 20075.40 ca.*−0.2 gravel, −0.5 sand
168–14 July 20074.60 ca.*−0.8 sand
1722 October–06 November 20073.60 ca.*−1.0  sand
189–20 November 20072.65 ca.*−0.95 sand
1922 February–4 March 20081.70 ca.*−0.95  sand
2017–21 March 20080.75 ca.*−0.95 sand
2126–31 March 20080.00*−0.75 sand

*The reference height is not exactly at the centreline, but at a distance where, after the creep settlement, the embankment height is 6.30 m.