Health Monitoring of Nuclear Structure Containment Using Strain Gauges to Assess the Integrity

Table 1

Chronological events of proof test and ILRT.

Sl. no.Activity

1Zero run-up test started after RB box up for PC ILRT
2Pressurization started
3Pressure reached at 0.35 kg/cm2 (g)
4Pressurization started after temp stabilisation and rundown at 0.35 kg/cm2 (g)
5Pressure reached at 0.7 kg/cm2 (g)
6Pressurization started after temp stabilisation and rundown at 0.7 kg/cm2 (g)
7Pressure reached at 1.06 kg/cm2 (g)
8Pressurization started after temp stabilisation and rundown at 1.06 kg/cm2 (g)
9Pressure reached at 1.4 kg/cm2 (g)
10Pressurization started after pressure stabilisation and strain/deflection data collection
11Pressure reached—1.73 kg/cm2 (g)
12Depressurization started after pressure stabilisation and strain/deflection data collection
13Pressure reached—1.4 kg/cm2 (g)
14Depressurization started after pressure stabilisation and strain/deflection data collection
15Pressure reached—1.06 kg/cm2 (g)
16Depressurization started after temp stabilisation, rundown and superimposition test at 1.06 kg/cm2 (g)
17Pressure reached—0.7 kg/cm2 (g)
18Depressurization started after temp stabilisation and rundown at 0.7 kg/cm2 (g)
19Pressure reached—0.35 kg/cm2 (g)