Research Article
Magnitude of Construction Cost and Schedule Overruns in Public Work Projects
Table 5
Mean and median values of schedule overrun by project factors.
| Project factors | Categories | No. of projects | Construction schedule overrun (%) | Mean | Median | Standard Deviation |
| Project types | Flood control | 83 | 3.19 | 2.53 | 34.71 | Transportation | 236 | 1.05 | 6.25 | 36.22 | Utilities | 44 | 1.02 | 0.00 | 39.70 |
| Project size | Less than $1 million | 135 | −11.23 | 0.00 | 43.37 | $1 million to $5 million | 128 | 4.99 | 6.25 | 33.39 | Greater than $5 million | 100 | 14.35 | 14.82 | 20.52 |
| Project construction duration | Less than 1 year | 279 | −4.56 | 0.00 | 38.12 | Greater than 1 year | 84 | 21.79 | 19.92 | 17.87 |
| Project completion year | 1991 to 2000 | 185 | 4.23 | 1.96 | 29.02 | 2001 to 2008 | 178 | −1.27 | 7.05 | 42.35 |
| Total projects | | 363 | 1.54 | 5.06 | 36.23 |
|
|