Magnitude of Construction Cost and Schedule Overruns in Public Work Projects

Table 5

Mean and median values of schedule overrun by project factors.

Project factorsCategoriesNo. of projects Construction schedule overrun (%)
Mean MedianStandard Deviation

Project typesFlood control833.192.5334.71
Transportation2361.056.2536.22
Utilities441.020.0039.70

Project sizeLess than $1 million135−11.230.0043.37
$1 million to $5 million1284.996.2533.39
Greater than $5 million 10014.3514.8220.52

Project construction durationLess than 1 year279−4.560.0038.12
Greater than 1 year8421.7919.9217.87

Project completion year1991 to 20001854.231.9629.02
2001 to 2008178−1.277.0542.35

Total projects3631.545.0636.23