Magnitude of Construction Cost and Schedule Overruns in Public Work Projects
Table 7
ANOVA results for construction cost and schedule overrun by project types.
| Project types | Unit | Mean | value | value | -critical |
| Construction cost overrun | | | Flood control | % | 3.04 | 1.646 | 0.194 | 3.020 | Transportation | % | 3.23 | Utilities | % | 1.27 | Construction schedule overrun | | | Flood control | % | 3.19 | 0.111 | 0.895 | 3.020 | Transportation | % | 1.05 | Utilities | % | 1.02 |
|
|