Table 1

Project information.

IDActivity descriptionPre.Time-cost functionType

1Site preparationā€”Discrete

2Forms and rebars1Discrete

3Excavation1Discrete

4Precast concrete girders1Discrete

5Pour foundation and piers2, 3, , , , Discrete

6Deliver precast concrete girders4ā€‰Nonlinear

7Erect girders5, 6ā€‰Piecewise linear
ā€‰

8Finish up7Linear