Risk Determination, Prioritization, and Classifying in Construction Project Case Study: Gharb Tehran Commercial-Administrative Complex

Table 2

Matrix of final weights of the group of risks.

Group of risksFuzzy weightFinal relative weightRank

Economic factors(0.0059, 0.1122, 4.5749)0.10841
Project management(0.0059, 0.1134, 4.5680)0.10842
Partners (0.0061, 0.1089, 4.2552)0.10123
Execution (0.0047, 0.0969, 4.1197)0.09724
Human resource(0.0047, 0.0969, 4.1197)0.09705
Political (0.0038, 0.0820, 3.7043)0.08706
Legal factors(0.0036, 0.0816, 3.6879)0.08667
Environmental and social (0.0032, 0.0753, 3.5225)0.08258
Resources and equipment(0.0029, 0.0722, 3.4371)0.08049
Planning and scheduling(0.0023, 0.0657, 3.2821)0.076510
Design (0.0026, 0.0657, 3.2078)0.074911