Identification of Risks Pertaining to Abandoned Housing Projects in Malaysia

Table 4

Response on construction.

ConstructionProbabilityFrequencyPercentValid percentCumulative percent

Delay of projectVery low probability
Low probability
Moderate probability
High probability1947.547.547.5
Very high probability2152.552.5100.0
Total40100.0100.0

Shortage of labour/manpowerVery low probability12.52.52.5
Low probability2557.5
Moderate probability16404047.5
High probability1332.532.580
Very high probability82020100
Total40100100

Shortage of equipmentVery low probability
Low probability6151515
Moderate probability16404055
High probability1742.542.597.5
Very high probability12.52.5100
Total40100100

Low performance by labourVery low probability717.517.517.5
Low probability14353552.5
Moderate probability16404092.5
High probability25597.5
Very high probability12.52.5100
Total40100100

Poor construction planning by contractorVery low probability
Low probability12.52.52.5
Moderate probability512.512.515
High probability14353550
Very high probability205050100
Total40100100