The Use of Project Time Management Processes and the Schedule Performance of Construction Projects in Mexico
Table 10
Correlation coefficients between mean SV values and UI values.
| Groups of processes | Periods of time | 4th week | 8th week | 12th week | Last week |
| Schedule planning | 0.41 | 0.30 | 0.27 | 0.37 | Schedule controlling | 0.46 | 0.49 | 0.47 | 0.51 | Total project | 0.50 | 0.43 | 0.40 | 0.49 |
|
|