The Use of Project Time Management Processes and the Schedule Performance of Construction Projects in Mexico

Table 4

Use Indexes (UI) for the Project Time Management processes.

ProcessesProjects
1234567891011121314

UI for schedule planning0.510.530.400.510.600.600.600.600.550.380.510.400.530.38
Activity definition 0.600.800.600.801.000.800.801.000.400.401.000.600.400.60
Activity sequencing0.670.670.500.580.830.670.670.750.580.330.580.330.580.42
Activity resource estimating 0.570.430.290.710.290.290.430.570.570.570.140.570.710.57
Activity duration estimating 0.800.400.400.400.800.400.400.600.800.400.600.400.200.20
Schedule development 0.330.460.330.380.460.670.630.460.500.330.460.330.540.29

UI for schedule controlling 0.330.460.250.330.460.420.380.750.330.380.540.210.330.42
Schedule monitoring 0.350.470.290.350.530.410.410.710.410.470.470.240.350.47
Schedule control 0.671.000.330.670.330.670.671.000.330.331.000.330.670.67
Total UI0.450.510.350.450.560.550.530.650.480.380.520.340.470.39