Research Article
The Use of Project Time Management Processes and the Schedule Performance of Construction Projects in Mexico
Table 4
Use Indexes (UI) for the Project Time Management processes.
| Processes | Projects | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| UI for schedule planning | 0.51 | 0.53 | 0.40 | 0.51 | 0.60 | 0.60 | 0.60 | 0.60 | 0.55 | 0.38 | 0.51 | 0.40 | 0.53 | 0.38 | Activity definition | 0.60 | 0.80 | 0.60 | 0.80 | 1.00 | 0.80 | 0.80 | 1.00 | 0.40 | 0.40 | 1.00 | 0.60 | 0.40 | 0.60 | Activity sequencing | 0.67 | 0.67 | 0.50 | 0.58 | 0.83 | 0.67 | 0.67 | 0.75 | 0.58 | 0.33 | 0.58 | 0.33 | 0.58 | 0.42 | Activity resource estimating | 0.57 | 0.43 | 0.29 | 0.71 | 0.29 | 0.29 | 0.43 | 0.57 | 0.57 | 0.57 | 0.14 | 0.57 | 0.71 | 0.57 | Activity duration estimating | 0.80 | 0.40 | 0.40 | 0.40 | 0.80 | 0.40 | 0.40 | 0.60 | 0.80 | 0.40 | 0.60 | 0.40 | 0.20 | 0.20 | Schedule development | 0.33 | 0.46 | 0.33 | 0.38 | 0.46 | 0.67 | 0.63 | 0.46 | 0.50 | 0.33 | 0.46 | 0.33 | 0.54 | 0.29 |
| UI for schedule controlling | 0.33 | 0.46 | 0.25 | 0.33 | 0.46 | 0.42 | 0.38 | 0.75 | 0.33 | 0.38 | 0.54 | 0.21 | 0.33 | 0.42 | Schedule monitoring | 0.35 | 0.47 | 0.29 | 0.35 | 0.53 | 0.41 | 0.41 | 0.71 | 0.41 | 0.47 | 0.47 | 0.24 | 0.35 | 0.47 | Schedule control | 0.67 | 1.00 | 0.33 | 0.67 | 0.33 | 0.67 | 0.67 | 1.00 | 0.33 | 0.33 | 1.00 | 0.33 | 0.67 | 0.67 | Total UI | 0.45 | 0.51 | 0.35 | 0.45 | 0.56 | 0.55 | 0.53 | 0.65 | 0.48 | 0.38 | 0.52 | 0.34 | 0.47 | 0.39 |
|
|