The Use of Project Time Management Processes and the Schedule Performance of Construction Projects in Mexico

Table 5

Results of the Schedule Performance Indexes in the observed projects.

WeeksDelayed projectsProjects completed on time
1345910122678111314

10.240.840.230.910.710.140.021.004.351.411.062.951.040.45
20.310.800.220.540.360.070.501.242.521.030.942.420.750.36
30.400.860.180.930.810.100.341.282.140.840.921.970.520.77
40.391.020.161.000.861.110.251.401.600.781.121.660.390.77
50.560.990.171.060.960.890.201.321.550.741.061.500.310.72
60.660.980.531.040.911.360.431.231.350.750.951.410.460.77
70.670.910.821.000.801.380.551.131.330.780.911.270.580.83
80.760.980.981.040.861.330.621.051.280.880.881.190.610.86
90.751.010.981.000.871.300.821.021.210.890.801.110.540.88
100.830.980.921.011.121.190.840.981.161.030.941.090.760.91
110.770.930.971.001.021.080.870.971.171.021.051.050.740.90
120.930.920.941.001.020.990.941.001.131.001.161.040.760.93
130.920.920.980.940.950.930.891.081.011.081.020.980.93
140.930.891.000.880.880.890.941.041.001.001.001.00
150.870.820.870.831.001.010.93
160.790.960.781.001.00
170.761.000.75
180.750.71
191.000.74

Projects that were granted an extension of time.