Research Article

The Use of Project Time Management Processes and the Schedule Performance of Construction Projects in Mexico

Table 6

Mean SPI values obtained for different periods of time.

ProjectsPerformance at project completionMean SPI values
4th week8th week12th weekLast week

1Delayed0.330.500.610.65
2On time1.001.001.001.00
3Delayed0.880.920.940.93
4Delayed0.200.410.590.65
5Delayed0.850.940.960.92
6On time1.001.001.001.00
7On time1.000.900.930.94
8On time1.001.000.980.99
9Delayed0.680.780.860.88
10Delayed0.360.800.910.87
11On time1.001.001.001.00
12Delayed0.280.370.530.62
13On time0.670.580.620.68
14On time0.590.690.760.79

Projects that were granted an extension of time.