The Use of Project Time Management Processes and the Schedule Performance of Construction Projects in Mexico

Table 7

Correlation coefficients between mean SPI values and UI values.

Groups of processesPeriods of time
4th week8th week12th weekLast week

Schedule planning0.560.410.370.40
Schedule controlling0.560.600.580.60
Total project0.640.560.520.55